Project Limits: Approximately 1-mile stretch of Northline Road between Middlebelt Road to Inkster Road.

Project Description: Concrete patches with joint repairs and HMA overlay.

Traffic Impact/Detour: Construction will be broken up into two stages to maintain traffic on Northline Rd. During Stage 1, the two-way center left-turn lane and adjacent westbound lane and eastbound lane will be closed to traffic. The outside westbound and eastbound lanes will be open to traffic. During Stage 2, the outside westbound and eastbound lanes will be closed to traffic, while the two-way center left-turn lane and adjacent westbound and eastbound lanes will be open to traffic.

Schedule: This project will begin in April 2024 and continue to August 2024.

PROJECT UPDATE:

Additional notifications will be provided to those within the project limits throughout the construction process as necessary.